Calibre - Carmichael Mine

SchedulingScheduling
Owners RepresentationOwners Representation
Claims ConsultingClaims Consulting
Forensic SchedulingForensic Scheduling
TrainingTraining

Calibre - Carmichael Mine

Calibre Global was awarded an engineering services contract in 2013 for mine infrastructure in relation to Adani Mining’s Carmichael Coal Mine and Rail Project.

Planned as part of a staged ramp-up, Adani are proposing to establish a combined open cut and underground coal mine involving the development of multiple greenfield open-cut and underground mines, supported by rail facilities leading to the Abbott Point Coal Terminal in the Galilee Basin, Central Queensland.

The scale of the project is extensive and includes mine infrastructure and associated mine processing facilities and offsite infrastructure.

Dynamic CPM Consulting developed the P6R8.3 schedules for the Bankable Feasibility Suitability (BFS) study. The schedule was built to a level 4 specification and was cost and resource loaded. Resources leveling and utilization for the mine camp was performed as well as a risk assessment.

Calibre - Carmichael Mine

Perth to Mandurah Rail

SchedulingScheduling
Owners RepresentationOwners Representation
Claims ConsultingClaims Consulting
Forensic SchedulingForensic Scheduling
TrainingTraining

Perth’s Mandurah railway line is not only an outstanding success for this year’s AusRAIL host city, but has become a national benchmark of success.

The line, which has become a touchstone for the industry nationally, is the primary reason behind an amazing 57.5% jump in urban passenger rail travel in Perth in just three years, from 35.8m total boardings in 2006/2007 to 56.4m in 2009/2010.

The 73km southern suburbs line was officially opened on December 23, 2007, and started regular operations the following day. Within six months it was one of the busiest lines on the Transperth network.

(Jennifer Perry, Rail Express)

Dynamic CPM Consulting performed a claim that was in the Perth Supreme Court. Our consultants performed a forensic schedule analysis on the rail progress schedules provided to the owner by the contractor. The findings were used to win the negotiations and resolve the claim, thus avoiding court. Once the contractor was faced with Dynamic CPM Consulting's findings, they agreed to settle. Our consultants also wrote an expert report to record the findings.

Perth to Mandurah Rail

CC

Canberra Hospital - JMA Architecture Owners Representation

SchedulingScheduling
Owners RepresentationOwners Representation
Claims ConsultingClaims Consulting
Forensic SchedulingForensic Scheduling
TrainingTraining

Canberra Hospital

Canberra Hospital (TCH) is the region's major public hospital, providing specialist and acute care to more than 500,000 people. TCH is a tertiary level health facility, and a teaching hospital of the Australian National University (ANU) Medical School.

Dynamic CPM Consulting, provided owners representation for JMA Architecture in Sydney. Our consultants put together the level 4 program schedule for the hospital expansion. Additionally JMA was awarded the contract due to the owner's representation services to be provided by Dynamic CPM Consulting. These services include contract oversight, Schedule update evaluation, critical path management and near critical path activity management with a monthly narrative and time impact analysis performed as required. Additionally, Dynamic CPM Consulting was to help oversee the contract and schedule and monitor the performance and progress of the work by the contractor.

Canberra Hospital - JMA Architecture Owners Representation

Las Vegas Airport - Skybridge

SchedulingScheduling
Owners RepresentationOwners Representation
Claims ConsultingClaims Consulting
Forensic SchedulingForensic Scheduling
TrainingTraining

Las Vegas Airport

McCarran International Airport (IATA: LAS), also known as Las Vegas Airport is the main commercial airport in Las Vegas and the entire area of Clark County, Nevada. Las Vegas airport is located 8 km south of the business district of Las Vegas in the town of Paradise. It covers an area of 1,100 ha and has four runways.McCarran Las Vegas Airport serves as a hub for Great Lakes Airlines. It serves as a focus city for Allegiant Air and Southwest Airlines; It is named after the former Nevada Senator Pat McCarran.

Our Director worked for the contractor, and put all the project schedules together, as well as maintained the monthly update and narrative submission. Our director performed weekly job walks and bi-weekly contractor meetings. A Time Impact Analysis was also performed and submitted against Bechtel and our client was awarded time and fees for impacts due to the owner.

Las Vegas Airport - Skybridge

CC

INEL Nuclear

SchedulingScheduling
Owners RepresentationOwners Representation
Claims ConsultingClaims Consulting
Forensic SchedulingForensic Scheduling
TrainingTraining

Idaho National Laboratory

Idaho National Laboratory is the Department of Energy's lead nuclear energy research and development facility. Building upon its legacy responsibilities, infrastructure and expertise, INL' s nuclear energy mission is to develop advanced nuclear technologies that provide clean, abundant, affordable and reliable energy to the United States and the world.

Our Director was a Project Controls Engineer (PCE). She put together schedule, budgets, cost and resources. Performed earned value reporting monthly, trending analysis, cost controls and transfers, and acquired our funding from DOE on a yearly basis for, TMI (Three Mile Island Fuel), ICDF (INEL Cercla Disposal Faciltiy), ER (Environmental Restoration), and 3100 Metres.

INEL Nuclear

CC

Savannah US Army Corps of Engineers

SchedulingScheduling
Owners RepresentationOwners Representation
Claims ConsultingClaims Consulting
Forensic SchedulingForensic Scheduling
TrainingTraining

Savannah  US Army Corps of Engineers 

The United States Army Corps of Engineers is a U.S. federal agency under the Department of Defense and a major Army command made up of some 36,500 civilian and military personnel making it one of the world's largest public engineering, design, and construction management agencies.

Our Company Director, was on the scheduling interface team. Her team was responsible for migrating the USACE  to P3Ec and were the first team to have a successful migration on time and under budget with no errors.

 
Savannah  US Army Corps of Engineers

Station Casinos Headquarters

SchedulingScheduling
Owners RepresentationOwners Representation
Claims ConsultingClaims Consulting
Forensic SchedulingForensic Scheduling
TrainingTraining

Station Casino Headquarters

Station Casinos is the leading provider of gaming and entertainment in Las Vegas, Nevada. Station's properties are regional entertainment destinations and include various amenities, including numerous restaurants, entertainment venues, movie theaters, bowling and convention/banquet space, as well as traditional casino gaming offerings such as video poker, slot machines, table games, bingo and race and sports wagering.

Our Company Director put together the schedules for the contractor and updated them monthly for the contractor. Meschelle helped them to achieve a successful completion and maintain the relationship with the owners

Station Casinos Headquarters

Nevada Department of Transport - Blue Diamond & I-15 Widening

SchedulingScheduling
Owners RepresentationOwners Representation
Claims ConsultingClaims Consulting
Forensic SchedulingForensic Scheduling
TrainingTraining

Nevada Department of Transport - Blue Diamond & I-15 Widening

One of the biggest issues facing Nevada DOT is the Las Vegas area has been growing very fast with projections of further growth. This growth has taxed highway system's capacity with congestion that needs to be addressed as well as other highways on the system throughout the valley. The solution was building highways and bridges to address capacity. (Case Study)

Our Company Director performed owners representation on various projects for the Nevada Department of Transport. 

Nevada Department of Transport - Blue Diamond & I-15 Widening

Clark County Schools

SchedulingScheduling
Owners RepresentationOwners Representation
Claims ConsultingClaims Consulting
Forensic SchedulingForensic Scheduling
TrainingTraining

Clark County Schools

The Clark County School District, as of 2012, is the fifth largest school district in the United States. It serves all of Clark County, Nevada, including the cities of Las Vegas, Henderson, North Las Vegas, Boulder City, and Mesquite; plus the census-designated places of Laughlin, Blue Diamond, Logandale, Bunkerville, Goodsprings, Indian Springs, Mount Charleston, Moapa, Searchlight, and Sandy Valley (Wikipedia).

Our Company Director performed a variety of roles to provide the best outcome for the Clark County School District. Our director put together a level 4 program schedule and provided Owners Representation. This included: Contract oversight, schedule update evalutaion, critical path management and near critical path activity management with a monthly narrative and time impact analysis performed as required

Clark County Schools

Palms Place

SchedulingScheduling
Owners RepresentationOwners Representation
Claims ConsultingClaims Consulting
Forensic SchedulingForensic Scheduling
TrainingTraining

Palms Place

Palms Place Hotel and Spa is a full service boutique hotel. Comfortably removed from the non-stop action of the Palms casino, this tower is a study in elegance and relaxation at Las Vegas.

Our consultants helped the primary contractor put together and manage the weekly and monthly schedules to the owner.

Palms Place

CC

Endeavour Energy - PMO

SchedulingScheduling
Owners RepresentationOwners Representation
Claims ConsultingClaims Consulting
Forensic SchedulingForensic Scheduling
TrainingTraining

Endeavour Energy

Endeavour Energy is responsible for the safe and reliable supply of electricity to 2.2 million people in households and businesses across Sydney’s Greater West, Blue Mountains, Southern Highlands and the Illawarra.

Dynamic CPM Consultantsworked for Major Projects A and the PMO. Our consultants oversaw around 150 substations. Dynamic CPM Consultants developed a reporting process for Endeavour Energy which included an executive summary to management and the PMO, monthly status updates and progress reports. Our consultants put together narratives, attended meetings, and put together Time Impact Analysis for claims on substations. 

Endeavour Energy - PMO